This is our humble abode. Moved in on 8/1/08
We are building a garage off to the side of our house for all of John's "stuff ". It will also have an exercise room, a bathroom and a loft off to the back for guests to stay...
This shows the garage footprint, basketball court, and hole for the built-in trampoline... the same hole that I found Royce climbing up out of the other day...
We've got cement on 10/17/08...
Finally started framing on 10/24/08. I think even John is a little surprised at how tall it is.
More framing on 10/27/08
This shows the loft over the bathroom area.
We've got a roof 12/08...

View from the backyard
Drywall 12/08

Cabinets & granite 12/08
Stucco is done...
Doors, paint & travertine 12/28/08...
John helped paint the inside.
Bathroom shower tile. John also helped Sterling with this. It looks great!